1. Question
On 1st April 2022, Green Build Limited (herein after referred to as “the company”) enters into a four-year contract (2022–2025) with MetroCity Council to design, build, and commission a new urban bridge, with a fixed fee of Rs. 100 crore and a Rs. 20 crore performance bonus payable only if 90 % completion is achieved by 31st March, 2024, i.e., end of the third year.
As the project gets underway, only 20% of the work is completed by the 1st year-end. Based on the project’s early stage and uncertainties such as potential delays due to weather, material supply issues, or regulatory clearances, the company estimates it is unlikely to meet the 90% milestone by the end of 2024.
By the end of Year 2, progress improves significantly, and 60% of the bridge is completed. This milestone brings new insights into project pace and resource capabilities, prompting the company to revise its projection. It now estimates that reaching 90% completion by the end of 2024 is probable. At the end of the third year, the company achieved 90% completion.
State how the revenue in such a case shall be recognised by the company over the contract period in accordance with the Ind AS framework.
2. Relevant provision
Ind AS 115: Revenue from contracts with customers
Para 39- For each performance obligation satisfied over time in accordance with paragraphs 35–37, an entity shall recognise revenue over time by measuring the progress towards complete satisfaction of that performance obligation. The objective when measuring progress is to depict an entity’s performance in transferring control of goods or services promised to a customer (ie the satisfaction of an entity’s performance obligation).
Para 40- An entity shall apply a single method of measuring progress for each performance obligation satisfied over time, and the entity shall apply that method consistently to similar performance obligations and in similar circumstances. At the end of each reporting period, an entity shall re-measure its progress towards complete satisfaction of a performance obligation satisfied over time.
Para 47- An entity shall consider the terms of the contract and its customary business practices to determine the transaction price. The transaction price is the amount of consideration to which an entity expects to be entitled in exchange for transferring promised goods or services to a customer, excluding amounts collected on behalf of third parties (for example, some sales taxes). The consideration promised in a contract with a customer may include fixed amounts, variable amounts, or both.
Para 50- If the consideration promised in a contract includes a variable amount, an entity shall estimate the amount of consideration to which the entity will be entitled in exchange for transferring the promised goods or services to a customer.
Para 51- An amount of consideration can vary because of discounts, rebates, refunds, credits, price concessions, incentives, performance bonuses, or other similar items. The promised consideration can also vary if an entity’s entitlement to the consideration is contingent on the occurrence or non-occurrence of a future event. For example, an amount of consideration would be variable if either a product was sold with a right of return or a fixed amount is promised as a performance bonus on achievement of a specified milestone.
Para 52- The variability relating to the consideration promised by a customer may be explicitly stated in the contract. In addition to the terms of the contract, the promised consideration is variable if either of the following circumstances exists:
(a) the customer has a valid expectation arising from an entity’s customary business practices, published policies or specific statements that the entity will accept an amount of consideration that is less than the price stated in the contract. That is, it is expected that the entity will offer a price concession. Depending on thejurisdiction, industry or customer, this offer may be referred to as a discount, rebate, refund or credit.
(b) Other facts and circumstances indicate that the entity’s intention, when entering into the contract with the customer, is to offer a price concession to the customer.
Para 53- An entity shall estimate an amount of variable consideration by using either of the following methods, depending on which method the entity expects to better predict the amount of consideration to which it will be entitled:
(a) The expected value – the expected value is the sum of probability-weighted amounts in a range of possible consideration amounts. An expected value may be an appropriate estimate of the amount of variable consideration if an entity has a large number of contracts with similar characteristics.
(b) The most likely amount—the most likely amount is the single most likely amount in a range of possible consideration amounts (ie the single most likely outcome of the contract). The most likely amount may be an appropriate estimate of the amount of variable consideration if the contract has only two possible outcomes (for example, an entity either achieves a performance bonus or does not).
Para 54- An entity shall apply one method consistently throughout the contract when estimating the effect of an uncertainty on an amount of variable consideration to which the entity will be entitled. In addition, an entity shall consider all the information (historical, current and forecast) that is reasonably available to the entity and shall identify a reasonable number of possible consideration amounts. The information that an entity uses to estimate the amount of variable consideration would typically be similar to the information that the entity’s management uses during the bid-and-proposal process and in establishing prices for promised goods or services.
Para 56- An entity shall include in the transaction price some or all of an amount of variable consideration estimated in accordance with paragraph 53 only to the extent that it is highly probable that a significant reversal in the amount of cumulative revenue recognised will not occur when the uncertainty associated with the variable consideration is subsequently resolved.
Para 59- At the end of each reporting period, an entity shall update the estimated transaction price (including updating its assessment of whether an estimate of variable consideration is constrained) to represent faithfully the circumstances present at the end of the reporting period and the changes in circumstances during the reporting period. The entity shall account for changes in the transaction price in accordance with paragraphs 87–90.
Para 87- After contract inception, the transaction price can change for various reasons, including the resolution of uncertain events or other changes in circumstances that change the amount of consideration to which an entity expects to be entitled in exchange for the promised goods or services.
Para 88- An entity shall allocate to the performance obligations in the contract any subsequent changes in the transaction price on the same basis as at contract inception. Consequently, an entity shall not reallocate the transaction price to reflect changes in stand-alone selling prices after contract inception. Amounts allocated to a satisfied performance obligation shall be recognised as revenue, or as a reduction of revenue, in the period in which the transaction price changes.
Para 89- An entity shall allocate a change in the transaction price entirely to one or more, but not all, performance obligations or distinct goods or services promised in a series that forms part of a single performance obligation in accordance with paragraph 22(b) only if the criteria in paragraph 85 on allocating variable consideration are met.
Click Here To Read The Full Story
Disclaimer: The content/information published on the website is only for general information of the user and shall not be construed as legal advice. While the Taxmann has exercised reasonable efforts to ensure the veracity of information/content published, Taxmann shall be under no liability in any manner whatsoever for incorrect information, if any.

Taxmann Publications has a dedicated in-house Research & Editorial Team. This team consists of a team of Chartered Accountants, Company Secretaries, and Lawyers. This team works under the guidance and supervision of editor-in-chief Mr Rakesh Bhargava.
The Research and Editorial Team is responsible for developing reliable and accurate content for the readers. The team follows the six-sigma approach to achieve the benchmark of zero error in its publications and research platforms. The team ensures that the following publication guidelines are thoroughly followed while developing the content:
- The statutory material is obtained only from the authorized and reliable sources
- All the latest developments in the judicial and legislative fields are covered
- Prepare the analytical write-ups on current, controversial, and important issues to help the readers to understand the concept and its implications
- Every content published by Taxmann is complete, accurate and lucid
- All evidence-based statements are supported with proper reference to Section, Circular No., Notification No. or citations
- The golden rules of grammar, style and consistency are thoroughly followed
- Font and size that’s easy to read and remain consistent across all imprint and digital publications are applied

CA | CS | CMA